SIERRA ONE STAYS
PLUMBING PLAN — DOMESTIC WATER SUPPLY + DWV
SHEET P-1.0
NORTH OF HEBER, AZ — NAVAJO COUNTY
JULY 2026 — PRELIMINARY
OFF-GRID: 10,000 GAL STORAGE TANK | PRESSURE SYSTEM | UV FILTRATION | TANKLESS WH (x2) | LOW-FLOW FIXTURES | SEPTIC SYSTEM
DOMESTIC WATER SUPPLY
- Source: 10,000 gal polyethylene storage tank (exterior)
- Pressure tank: 80 gal diaphragm, 40-60 PSI, in equip room
- Filtration: sediment pre-filter + UV sterilization (equip room)
- Main supply: 1-1/2" PEX-A from tank, reduced to 1" main
- Hot water: (2) tankless heaters in parallel (Rinnai RUR199iN or equiv.)
- LP gas supply to tankless heaters — dedicated regulator + shutoff
- Recirculation: dedicated 1/2" return loop w/ Grundfos pump
- Timer + aquastat control: runs only during occupied hours
- Branch lines: 1/2" PEX-A home runs from main to each fixture
- Shutoff valves at each room group and at each fixture
- PEX-A rated for freeze protection — all lines insulated R-4 min
- Isolation valves at equip room for full system shutdown
DRAIN / WASTE / VENT
- Main drain: 4" PVC SCH 40 along rear wall, 1/8" per ft slope
- Toilet drains: 3" PVC to main (low-flow 1.28 GPF fixtures)
- Shower drains: 2" PVC to main
- Lavatory drains: 1-1/2" PVC with P-trap to main
- Vent risers: 2" PVC through roof at every 3rd bay (4 total)
- Horizontal vent tie: 2" PVC connecting all VTR risers
- Cleanouts: (5) at max 60' intervals per IPC
- Main drain exits building at center to septic system
- ADA fixtures per ANSI A117.1 — grab bars, mounting heights
- All DWV per IPC 2018 as adopted by Navajo County
SEPTIC SYSTEM
- Engineered septic per Navajo County / ADEQ requirements
- Permit required prior to construction — perc test on file
- 1,500+ gallon concrete septic tank (sized per fixture count)
- Engineered drain field per soil conditions
- Distribution box between tank and field
- Min 100' setback from water tank per ADEQ
- Grease interceptor recommended for any future kitchen drain
- Cleanout at building exit and at tank inlet
- Navajo County inspection required at each phase